Build ScheduleTentative (i.e. not finalized; see also rough or thumbnail sketch) Build Schedule:
| Week |
Date |
Activity |
| 1 |
April 23-24 |
Raise the Roof; Ground Blessing - DONE!
|
| 2 |
April 30 - May 1 |
NO BUILD; DERBY WEEKEND |
| 3 |
May 7-8 |
Blocking; Install windows & doors - DONE!
|
| 4 |
May 14-15 |
Begin soffitt, siding, fascia
|
| 5 |
May 21-22 |
Siding & insulation
|
| 6 |
May 28-29
|
NO BUILD; MEMORIAL WEEKEND |
| 7 |
June 4-5 |
Siding, soffitt, fascia; begin hanging drywall
|
| 8 |
June 11-12 |
Hang drywall; finish siding
|
| 9 |
June 18-19 |
Paint trim (Construction Center?) |
| 10 |
June 25-26 |
Hang gutters; finish hanging drywall |
| 11 |
July 2-3 |
NO BUILD; INDEPENDENCE WEEKEND |
| 12 |
July 9-10 |
Prime/paint ceilings & walls; begin shed |
| 13 |
July 16-17 |
Hang doors; install luan; work on shed
|
| 14 |
July 23-24 |
Interior trim, paint, caulk
|
| 15 |
July 30-31 |
Finish trim & hardware, caulk & touch-up paint
|
| 16 |
August 6-7 |
Fri - Prep for dedication; Sat - Dedication |
|
|