2002 Project House: 2721 Garland Avenue
"Roof Raising" Weekend
05/09/02:
The starting point - decking in place
awaiting the house.

05/10/02:
First day of work - all exterior and interior walls in place by end of day.

05/11/02:
All roof trusses positioned, rakes attached, roof sheeting 75% completed.
Ground blessing ceremony held at lunchtime.

05/17/02:
Rainy day. Front window and door installed. Attic prepared for flooring.
Roof boards were completed on Wednesday by some volunteers from Mars Hill, NC.
Some plumbing and electrical work done. Roof felt installed.

05/18/02:
All windows and rear entry door installed. Tyvek wrapped around full
exterior. Gutter boards prepared. Rear storage space covered with OSB. Starter
strips for vinyl placed. Drip edge placed along roof line. Attic stairway
installed. Nailer boards for drywall put up.

05/24/02:
Shingles in place on about 1/2 of roof, vinyl corners and F/J channels in
place on most of house, soffit started, underneath porch roof begun.

05/25/02:
No work on Saturday due to holiday weekend.
05/31/02 & 06/01/02:
Roofing completed, including ridge vent. Vinyl siding and soffit completed
on east and west sides and about 25% complete on front and rear of house. Rear
storage room door installed. White metal bent for most areas.
Sorry, no photos... I was out of town.
|