2002 Project House: 2721 Garland Avenue
06/07/02:
Insulation completed both inside and under decking. Vinyl siding about 80%
complete. Special thanks to the crawlspace insulation team!

06/08/02:
Continued work on vinyl and began installing white metal. Ran out of siding
so about 5% remains unfinished, mainly the front gable. White metal nearly
completed. Had to rework some vinyl around rear doors & window to get it lined
up properly.
06/14/02:
All vinyl siding and soffit completed. White metal completed. Installation
of porch posts and railings begins. Hanging of drywall begins.

06/15/02:
Porch railings completed, except for painting the filler blocks where the
rail attaches to the house. Ceiling drywall completed except for the bathrooms
and closets. Drywall covers about 45% of walls.

06/21/02:
Gutters installed. Hanging of drywall continues.

06/22/02:
Drywall hanging completed. 3 downspouts installed on gutters.
06/28/02:
Painting day at Habitat warehouse: doors, trim pieces, etc. Fourth downspout
hung on house and all drywall scrap removed from inside house. Bobcat dozer used
to clear large concrete chunks from yard and fill holes/smooth yard.

06/29/02:
More painting at warehouse. Final downspout put in place.
|