2002 Project House: 2721 Garland Avenue
07/05/02:
Prepared forms for pouring of rear patio & sidewalk along side of house.
Painting of shelves & trim at warehouse.

07/06/02:
Finalize forms for sidewalk. House numbers applied. More painting - exterior
doors, trim, etc.
07/12/02:
Painting party. All ceilings completed, 2 coats. Walls started.

07/13/02:
Painting blitz continues.
07/19/02:
Interior doors hung, kitchen cabinets started, painting winding down.

07/20/02:
Kitchen cabinets completed, baseboards and window trim started.
07/26/02:
Kitchen cabinets trimmed, touchup painting continues, baseboards completed
in all but 2 bathrooms, majority of closet shelves completed, sanding of floor
in preparation for hardwood install.

07/27/02:
Landscaping cleanup work, baseboard cut for bathrooms (but not installed),
tile floors completed in bathrooms (not grouted), more painting/caulk touchup,
hardwood floor laid in furnace closet.

|