2002 Project House: 2721 Garland Avenue
08/02/02:
Installation of hardwood flooring begun. Tile grout completed. Touchup
painting continues.

08/03/02:
Work on flooring continues.
08/09/02:
Hardwood flooring installation continues. Touchup painting, caulking, and
'punch list' items worked on.

08/10/02:
Hardwood floors completed. Landscaping of front yard.
08/16/02 & 08/17/02:
Landscaping, cleanup, and various final touches. Sorry, I was on vacation so no photos from this
weekend.
08/24/02:
House dedication.

|