2001 Project House: 1836 Baird Street
07/05/01:
Vinyl/aluminum work on front porch area & front of house.
07/06/01 & 07/07/01:
All vinyl work completed.
All insulation completed,
both inside the house and underneath in the crawlspace.
Interior is ready for
drywall, scheduled to begin Wednesday, July 11.
White metal completed except for
1 piece on rear gable.
| Special kudos to this 'crawlspace insulation crew': five
brave volunteers who donned these funky 'space suits' and crawled under
the house on a hot day to install the insulation! |
 |
|