2000 project house: 1717 Baird Street
July 21, 2000 - First work day:
Initial framing. About 2/3 roof trusses in place, some outer wallboards
installed.


07/22/2000:
"Raise the Roof" dedication ceremony, roof trusses complete,
roof boards & tarpaper installed.

07/27/2000:
Windows/doors cut out, housewrap in place, most drip edge installed.

07/29/2000:
Rain all day. Attic storage boards placed, most crawlspace insulation
installed.

|