First wall in place at 8:00am. Interior walls begun at 9:30am. Roof trusses
begun about 2pm and completed by 3:50pm.

06/27/03:
Our stack of OSB was missing about 50 sheets upon arrival Friday morning.
Porch beams placed and small trusses added, rakes installed on gables, roof and
side sheeting in place, and felt completed on roof by end of the day.

06/28/03:
Windows cut out and installed, weather-wrap completed, front door
installed, rear patio forms adjusted and prepared, attic stairs & flooring
completed. Ground blessing ceremony held at 11:30am with large crowd in
attendance.