2003 Project House: 1715 Crop Street
07/11/03:
Vinyl F/J channels & starter strip completed, vinyl corner posts in place,
attic stairs moved to kitchen area, octagon vent installed in front gable.

07/12/03:
Vinyl siding 95% completed on right side of house, 25% completed on front of
house. Many things are on hold until the electricians do their work inside.
07/18/03 & 07/19/03:
Vinyl siding 95% completed; White metal bent and partially installed;
crawlspace insulation completed; rear and storage exterior doors installed. If
anyone has photos from these days, please email them to me at
byron@ccum.net.
07/25/03:
All vinyl siding completed. Inside wall insulation completed. White metal on
porch completed & vinyl post installation begun. Interior doors & trim painted.

07/26/03:
All exterior white metal completed, porch posts & front railing complete.
Don't forget to check out the video clips.