2003 Project House: 1715 Crop Street

07/11/03:

Vinyl F/J channels & starter strip completed, vinyl corner posts in place, attic stairs moved to kitchen area, octagon vent installed in front gable.

07/12/03:

Vinyl siding 95% completed on right side of house, 25% completed on front of house. Many things are on hold until the electricians do their work inside.

07/18/03 & 07/19/03:

Vinyl siding 95% completed; White metal bent and partially installed; crawlspace insulation completed; rear and storage exterior doors installed. If anyone has photos from these days, please email them to me at byron@ccum.net.

07/25/03:

All vinyl siding completed. Inside wall insulation completed. White metal on porch completed & vinyl post installation begun. Interior doors & trim painted.

07/26/03:

All exterior white metal completed, porch posts & front railing complete.